Grayfer Field Platform Complex Put into Operation

01.01.2023 All news

The ice-resistant fixed platform with a 25-well drilling package, the living quarters platform for 152 persons and the bridge between them have been handed over to the client. CNGS Engineering performed procurement of equipment and materials, fabrication, marine operations and commissioning.

The ice-resistant platform topsides weigh 9,117 t, the jackets 3,493 t and the 17 piles 2,796 t. The structures of both platforms were delivered and installed offshore in the course of marine operations in 2019–2022; the combined weight of jackets, topsides, piles and bridge exceeds 21,000 t.

Work at the field began in July 2018. In 2021 two 10 kV cable lines were laid to the platform from the LSP-1 platform of the V. Filanovsky field.

More in the project pages Grayfer Field Ice-Resistant Platform: Procurement, Fabrication, Commissioning, Grayfer Field LQ Platform and Bridge: Fabrication and Commissioning, Grayfer Field Platform Complex: Marine Operations and the Fixed Offshore Platforms service page.

01.lsp-topside-construction-2
02.lsp-topside-construction-3
03.lsp-topside-construction-4
01.lsp-topside-construction-2
02.lsp-topside-construction-3
03.lsp-topside-construction-4